Analysis · 2026-10-27
What a DPC™ review checks in an EPC contract: a worked example
An illustrative walk-through of the DPC™ checkpoints on a mid-sized EPC contract, from the change mechanism to the dispute board.
This worked example uses an illustrative contract, not a client matter: a USD 40 million EPC contract for a solar plant, with an Indian employer and a contractor based in Spain. It shows what a DPC™ Standard review looks at and the kind of fixes it records.
Checkpoint 1: the change mechanism
Most construction disputes start as variations. The review asks whether every change has a written instruction, a valuation rule and a time limit for the contractor's notice. The example contract allowed oral instructions "in an emergency" with no follow-up: the fix is a 48-hour written confirmation rule.
Checkpoint 2: notices and time bars
Time bars are only fair if both sides can see the clock. The fix here was one notice address per party, e-mail as a valid channel, and a register of notices kept by the engineer.
Checkpoint 3: escalation and the dispute board
The contract had a dispute adjudication board on paper but no procedure to appoint it. DPC™ recorded a standing board appointed at signature, with a fee cap, so issues are decided while the project runs.
Checkpoint 4: the arbitration clause and enforcement
Seat, rules, language, number of arbitrators and the law of the arbitration agreement were checked against where each party holds assets. The review confirmed a neutral seat in a New York Convention state and kept the right to court interim relief.
What the certificate records
The DPC™ certificate names the contract version by its fingerprint, the outcome of each checkpoint and the reviewing Fellow. Lenders can check the number in the public DPC™ Registry.